A larger group within public transport needed to develop, further build, and implement a vehicle maintenance system across multiple operations in parallel.
Close collaboration between project members, the system supplier, and strategic and operational units was central to the project's success.
Requirements capture for operational units
Responsible for all requirements capture through interviews, workshops, and collaboration with central functions and operational units. Documentation of requirements, functionality, acceptance criteria, and user guides.
Prioritisation of development focus
Through strong familiarity with the system's status and operational needs, a roadmap and prioritisation assessment was created to guide the system's development.
Securing delivery pace throughout the project
Management and coordination of progress on system development and the project's agile ways of working, ensuring efficient progress across all workstreams.
Quality assurance and sign-off
Responsible for all documentation, preparation, and execution of all tests, including functional tests, UAT, and system integration tests, in close collaboration with users and the system supplier.
Training, Go-live, and HyperCare
Planning and execution of go-live across multiple operational units. Training of end users and the system management organisation before and during implementation, with ongoing support after go-live.